January 20, 2017 W. Jackson Avenue Update -
NEWS RELEASE
KUB Completes W. Jackson Avenue Streetscapes Utilities
Upgrades
Ahead
of Schedule
KUB Underground
Construction crews have successfully completed all utility infrastructure
upgrades on W. Jackson Avenue nearly three months ahead of schedule. Utility
upgrades, the first step in the City’s overall streetscapes improvements
planned for this area, began in November 2016, and were expected to last
through April 2017. Through efficient planning, resource commitment, and
effective work management, KUB Underground Construction crews and staff reduced
the length of the project substantially while completing upgrades on
infrastructure that will serve this section of the Old City for many years to
come.
W. Jackson Avenue has
been fully reopened to normal traffic flow as of Friday, January 20.
As part of this
project, the utility infrastructure upgrades below were completed:
Water main installed: 950 feet
Water service lines
connected:
9
Natural gas main
installed:
1,000 feet
Natural gas service
lines connected:
5
Wastewater main
installed:
502 feet
Fire hydrants
replaced/installed:
5
Wastewater manholes
installed:
3
Wastewater service
lines connected:
3
To the extent possible,
KUB worked closely with businesses and residents in this area to coordinate
work and minimize the impact of service interruptions while also maintaining
access to buildings and parking areas. KUB appreciates its customers and their
patrons, and the City of Knoxville, for their ongoing patience and support as
the utility portion of this project was completed.
City streetscape
improvements are expected to follow on W. Jackson Avenue in the spring of 2017.
KUB is a municipal
utility serving Knox and parts of seven adjacent counties and provides
electric, natural gas, water, and wastewater services to more than 452,000
customers.
###.
January 20, 2017 N. Central Street/Fifth Avenue Update – This past week,
KUB’s contractor Adams and Sons, Inc., completed water line tie-ins on all
connecting side streets along Fifth Avenue, from Gay Street to Lamar Street.
Weather permitting, paving crews are scheduled to complete remaining roadway
surface restoration, remove traffic control devices, and reopen all lanes of
East and West Fifth Avenue, and the section of N. Central Street between
Magnolia Avenue and Fifth Avenue, to traffic by Monday, January 23, 2017.
Starting on Monday, January 23, Adams and Sons, Inc., will begin
the next stage of water main installation on the area of N. Central Street extending
from the Fifth Avenue intersection to the N. Broadway intersection. Both
northbound lanes and the northbound bicycle lane will be closed on this section
of N. Central Street. Traffic flow will be maintained in both directions,
however, with one northbound and one southbound lane shifting to the southbound
side of N. Central Street. Southbound bicycle traffic will merge with vehicle
traffic through the work zone. Vehicle traffic is advised to remain aware of
the ongoing presence of workers, equipment, traffic channeling devices,
barricades, and signs in this area. Note that the intersections of Fifth
Avenue, Fourth Avenue, and Third Avenue will remain open until work is required
in those areas. Work in this section is expected to last through early March. Follow
up notices will be issued ahead of any work requiring intersection closures in
this work zone.
(N.
Central Streetscapes Project) N. Central Street Lane Closure [January 23 – early March] – KUB and
its contractor will close both northbound lanes and the bicycle lane on N.
Central Street between the Fifth Avenue intersection and the N. Broadway
intersection at 6 a.m., Monday, January 23, through early March. Both northbound lanes and the northbound
bicycle lane will be closed on this section of N. Central Street. Traffic flow
will be maintained in both directions, however, with one northbound and one
southbound lane shifting to the southbound side of N. Central Street.
Southbound bicycle traffic will merge with vehicle traffic through the work
zone. Vehicle traffic is advised to remain aware of the ongoing presence of
workers, equipment, traffic channeling devices, barricades, and signs in this
area. Note that the intersections of Fifth Avenue, Fourth Avenue, and Third
Avenue will remain open until work is required in those areas. Follow up
notices will be issued ahead of any work requiring intersection closures in
this work zone.
No comments:
Post a Comment