Friday, December 27, 2019

South Knox Water & Wastewater Project Update

December 20, 2019 – KUB contract crews will close a section of Davenport Road between Boggs Avenue and Sherrod Road to through traffic continuously from 9 a.m., Monday, December 30, through 3 p.m., Friday, March 27, 2020, as work is performed on both the water distribution and wastewater collection system in the area. The roadway will reopen on weekends and holidays, and local traffic access will be maintained. Alternate routes include Atchley Street, Mimosa Avenue, and Sherrod Road.   

Friday, December 20, 2019

Holston-Chilhowee Area Wastewater Project (Mini-Basin 20A3)

December 20, 2019 – As a follow-up to construction notices that were mailed to area customers recently, the start for this project has been shifted to early- to mid-January 2020. Continue to follow this blog for weekly updates once construction begins.

Old Kingston Pike Water Main Project

December 20, 2019 – KUB Underground Construction crews have completed the installation of all new water mains and customer service line connections along Old Kingston Pike, Staub St and S. Forest Park Blvd. No work will be performed in this area until early January 2020. To minimize future disruptions in this area, KUB will follow the water main project with wastewater collection system upgrades in this same area starting in January 2020. Affected customers will be notified prior to the start of wastewater construction. Final overall paving and restoration will take place at the conclusion of the wastewater project.

Fountain City Natural Gas Project

December 20, 2019 – Contractor Classic City Mechanical will work in the following areas next week:
  • Connecting sections of natural gas mains at:
    • Grove Drive and Tansy Lane
    • Grove Drive and Belcourt Drive
    • Grove Drive and Edonia Drive
    • Ridgewood Road and Poplar Place
    • Ridgewood Rod and N. Broadway
    • Edonia Drive and Ridgewood Road
Holiday Schedule – Contractor crews will not work December 24-25. Due to holiday schedules, the next blog update will be posted on January 3, 2020.

Holston Hills Natural Gas Project

December 20, 2019 Update –Contractor East Tennessee Pipeline crews will work in the following areas next week:
  • Potholing to located existing buried utility lines and boring in new sections of natural gas main between 1120 Montview Road and Shady Dell Trail
  • Customer service line connections to the new natural gas main in the following areas:
    • 5212, 5213, 5300, 5308, 5312, 5313, 5317, 5400 Green Valley Drive
Holiday Schedule – Contractor crews will not work December 23-25. Due to holiday schedules, the next blog update will be posted on January 3, 2020.

Sequoyah Hills Wastewater Project

December 20, 2019 UPDATE - Construction crews will work in the following areas next week with intermittent road closures between 7 a.m. – 5 p.m.:
  • Taliluna Avenue between South Garden Road and Lakeland Drive
  • Whitlow Avenue between Bluff View Road and Cedarhill Road
Crews will also work in the following off-road easements with minimal traffic impacts:
  • Easements between Lakeland Drive and Taliluna Avenue
Holiday Schedule – Contractor crews will not work the week of December 23-27 in the Phase 2 area. Limited work will take place in the work zones identified on the attached map the week of December 30-January 3. Full construction activities will resume the week of January 6. Due to holiday schedules, the next blog update will be posted on January 3, 2020.

Closed-circuit Television Inspection – Crews will continue to work throughout the Phase 2 area next week. Temporary lane closures will be implemented as needed when crews are present.

Manhole Rehabilitation – Crews will work throughout the Phase 2 area next week. Temporary lane closures will be implemented as needed when crews are present.

Sequoyah Park – Morgan Construction and their subcontractors continue to break down the bypass pumping equipment and piping in the park. Cleanup and restoration of excavated areas also continues in the park. See the attached map showing current work corridors within the park. The park, all entrances and parking areas, and boat ramp remain open during this work. Morgan Construction is also maintaining a fenced area in the middle parking lot for equipment and materials storage. KUB has coordinated work in the park with City of Knoxville Parks and Recreation and the Kingston Pike Sequoyah Hills Association.

Natural Gas System Work – Crews have resumed natural gas inspection and maintenance work at various locations throughout Sequoyah Hills. This work may require short term traffic impacts in the immediate area where crews are working.

Friday, December 13, 2019

Old Kingston Pike Water Main Project

December 13, 2019 – KUB Underground Construction crews have completed the installation of all new water mains and customer service line connections along Old Kingston Pike, Staub St and S. Forest Park Blvd. Asphalt patching and restoration crews will continue to work in the area through next week. Road closures and lane shifts will continue in this area as needed. To minimize future disruptions in this area, KUB will follow the water main project with wastewater collection system upgrades in this same area starting in January 2020. Affected customers will be notified prior to the start of wastewater construction. Final overall paving and restoration will take place at the conclusion of the wastewater project.


Fountain City Natural Gas Project

December 13, 2019 – Contractor Classic City Mechanical will work in the following areas next week:
  • Potholing to located existing buried utility lines and boring in new sections of natural gas main in the following areas:
    • Ridgewood Road from Oak Road to N. Broadway
    • 5501-5524 Peyton Place
  • Connecting sections of natural gas mains at:
    • Grove Park and Brabson Drive
    • Grove Park and Walkup Drive
    • 2901 Brabson Drive
    • Edonia Drive and Weems road
    • Edonia Drive and Gresham Road
    • Edonia Drive and Van Horn Road
    • Edonia Drive and Ridgewood Road
  • Customer service line connections to the new natural gas main in the following areas:
    • 5760-5909 Grove Drive
    • 2900-2905 Edonia Drive
    • 1910 & 1911 Martha Berry Drive

Holston Hills Natural Gas Project

December 13, 2019 Update –Contractor East Tennessee Pipeline crews will work in the following areas next week:
  • Potholing to located existing buried utility lines and boring in new sections of natural gas main between 4701 and 4905 Westover Terrace and on Shady Lane between Shady Dell Trail and Westover Terrace
  • Customer service line connections to the new natural gas main in the following areas:
    • 5612, 5615, 5616, 5617 Crestwood Drive
    • 5317, 5320, 5321, 5325 Shady Dell Trail

Friday, December 6, 2019

Sequoyah Hills Wastewater Project


December 6, 2019 UPDATE – Construction crews will work in the following areas next week with intermittent road closures between 7 a.m. – 5 p.m.:
  • Taliluna Avenue between South Garden Road and Lakeland Drive
  • Whitlow Avenue between Bluff View Road and Cedarhill Road
Crews will also work in the following off-road easements with minimal traffic impacts:
  • Easements between Lakeland Drive and Taliluna Avenue
Closed-circuit Television Inspection – Crews will continue to work throughout the Phase 2 area next week. Temporary lane closures will be implemented as needed when crews are present.

Manhole Rehabilitation – Crews will work throughout the Phase 2 area next week. Temporary lane closures will be implemented as needed when crews are present.

Sequoyah Park – Morgan Construction and their subcontractors will begin to break down the bypass pumping equipment and piping in the park next week. Cleanup and restoration of excavated areas will also begin next week. See the attached map showing current work corridors within the park. The park, all entrances and parking areas, and boat ramp remain open during this work. Morgan Construction is also maintaining a fenced area in the middle parking lot for equipment and materials storage. KUB has coordinated work in the park with City of Knoxville Parks and Recreation and the Kingston Pike Sequoyah Hills Association. Informational banners have been placed in the park entrances/parking areas to provide park visitors with details about the wastewater rehabilitation work. Updates on the progress of work in the park will be posted weekly and as needed on this blog site.

Natural Gas System Work – Crews have resumed natural gas inspection and maintenance work at various locations throughout Sequoyah Hills. This work may require short term traffic impacts in the immediate area where crews are working.

Holston Hills Natural Gas Project


December 6, 2019 Update –Contractor East Tennessee Pipeline crews will work in the following areas next week:
  • Potholing to located existing buried utility lines and boring in new sections of natural gas main between 4701 and 4905 Westover Terrace and on Shady Lane between Shady Dell Trail and Westover Terrace
  • Customer service line connections to the new natural gas main in the following areas:
    • 5612, 5615, 5616, 5617 Crestwood Drive
    • 5317, 5320, 5321, 5325 Shady Dell Trail
    • 5610 Far Vista Lane

Fountain City Natural Gas Project


December 6, 2019 – Contractor Classic City Mechanical will work in the following areas next week:
  • Potholing to located existing buried utility lines and boring in new sections of natural gas main in the following areas:
    • Ridgewood Road from Oak Road to N. Broadway
    • 5501-5524 Peyton Place
  • Connecting sections of natural gas mains at:
    • Brabson Drive and Walkup Drive
    • Brabson Drive and Grove Park Drive
    • Edonia Drive and Grove Park Drive
    • Edonia Drive and Weems Road
    • Edonia Drive and Gresham Road
    • Edonia Drive and Van Horn Drive
  • Customer service line connections to the new natural gas main in the following areas:
    • 5760-5936 Grove Drive
    • 2813 & 2822 Pruden Drive
    • 1910 & 1911 Martha Berry Drive

Old Kingston Pike Water Main Project


December 6, 2019 – KUB Underground Construction crews have completed the installation of all new water mains along Old Kingston Pike, Staub St and S. Forest Park Blvd. Crews completed service connections along S. Forest Park Boulevard this past week, and work will continue on customer service lines and fire hydrant connections along Old Kingston Pike in the coming days. Road closures and lane shifts will continue in this area as crews dig to connect customer service lines to the new main and roadway asphalt patching follows. All construction associated with the water lines is scheduled for completion prior to the upcoming holidays. To minimize future disruptions in this area, KUB will follow the water main project with wastewater collection system upgrades in this same area starting in early January. Affected customers will be notified prior to the start of wastewater construction. Final paving and restoration will take place at the conclusion of the wastewater project.