July 28, 2017 N. Central Street Update – This past week, Adams and Sons, Inc., completed the remaining side street tie-in connections on East and West Scott Avenue to finish installation of all water main pipeline segments, service lines, and fire lines/hydrants up to the end of the project zone at Woodland Avenue.

Subcontractor crews will remain onsite through next week to complete any remaining asphalt/roadway restoration and general site cleanup.

All lanes previously closed in association with KUB utility work on N. Central Street have been reopened; however, limited traffic control measures will be implemented as needed for remaining restoration work next week. Accordingly, the traffic map issued with previous weekly blog updates is no longer required.