Friday, December 16, 2016

Project Update

December 16, 2016 N. Central Street Update – This week, KUB’s contractor Adams and Sons, Inc., continued water main installation work on W. Fifth Avenue, where the eastbound lane remains closed between N. Gay Street and Lamar Street (westbound lanes remain open).

Next week, work will continue on W. Fifth Avenue between N. Gay Street and Lamar Street, and on N. Central Street between W. Fifth Avenue and Magnolia Avenue. All traffic control measures will remain the same. Crews will not work Friday, December 23, or Monday, December 26, in observance of the Christmas holiday. All traffic control measures will remain in place during the holiday for public safety. Please see the N. Central Street traffic map in the right hand column of this blog for more detailed information.


December 16, 2016 W. Jackson Avenue Update
– This week, KUB Underground Construction Crews completed Phase 2 natural gas and water infrastructure work by installing new mains for both utilities in the currently established work zone. 

The current traffic control plan will remain in place through early next week as remaining utility work and paving are completed. Crews are scheduled to shift the work zone and road closure by the middle of next week to the area just west of Knox Whiskey Works and extending to the Southeastern Glass Building as work begins on Phase 3 of the project. An updated map will be issued next week ahead of the work zone and traffic control plan shift. Crews will not work Friday, December 23, or Monday, December 26, in observance of the Christmas holiday. All traffic control measures will remain in place during the holiday for public safety. Please see the W. Jackson Avenue traffic map in the right hand column of this blog for more detailed information.

No comments:

Post a Comment