February 3, 2017 N. Central Street/Fifth Avenue Update – This past week, KUB’s contractor Adams and Sons, Inc., completed installation of the new water main on the section of N. Central Street between Fifth Avenue and the N. Broadway intersection. Next week crews will prepare for testing on the new main, connect customer service lines, and coordinate tie-ins to connect side street lines to the new main.
Since starting in November 2016, Adams and Sons has completed nearly 42 percent of the overall project and installed approximately 2,800 feet of new main, including 12 connecting tie-ins, 65 customer service line connections, and 7 fire hydrants.
Vehicle traffic is advised to remain aware of the ongoing presence of workers, equipment, traffic channeling devices, barricades, and signs in this area. Note that the intersections of Fifth Avenue, Fourth Avenue, Third Avenue, and North Broadway will remain open until work is required in those areas. Work in this section is expected to last through early March. Follow up notices will be issued ahead of any work requiring intersection closures in this work zone.
Please see the current N. Central Street traffic map with the issue date of January 20, 2017 in the right hand column of this blog for the current traffic control plan and more detailed information.
No comments:
Post a Comment