Main installation will continue in the Bennington Drive area next week as crews proceed through the Vanosdale Road intersection. Boring crews are scheduled to begin work on Sheffield Drive and Corteland Drive next week.
Tie-up crews will begin connecting sections of main on Bennington Drive after Labor Day.
As a reminder, this project is scheduled to be completed in four zones over the next 18-24 months. Please see the Project Information Sheet & Map in the column to the right for more details related to this project.
This work may require temporary lane closures in the immediate work zone. Motorists and residents are also reminded to watch for the presence of workers, equipment, and vehicles in the area.
KUB will post weekly updates on this blog for the duration of the project.
Segments of plastic natural gas pipe installed by boring machine on Bennington Drive. Crews will return next week to connect the mains and complete installation. |