August 11, 2017 West Hills Area Natural Gas Main Replacement Project Update – KUB Underground Construction is scheduled to begin construction activity on Monday, August 14, as boring crews start pipeline installation on Bennington Drive, near Vanosdale Road.
Additional crews will begin work in this same area the following week to connect the new sections of pipe.
As a reminder, this project is scheduled to be completed in four zones over the next 18-24 months. Please see the Project Information Sheet & Map in the column to the right for more details related to this project.
This work may require temporary lane closures in the immediate work zone. Motorists and residents are also reminded to watch for the presence of workers, equipment, and vehicles in the area.
KUB will post weekly updates on this blog for the duration of the project.