October 13, 2017 West Hills Area Natural Gas Main Replacement Project Update – KUB Underground Construction (UGC) Crews finished connecting sections of newly-installed natural gas main on Bennington Drive, between Vanosdale Road and Sheffield Drive, this past week.
Additionally, crews were scheduled to complete boring work on Vanosdale Road this week, and tie-up the sections of main at the Bennington Drive and Vanosdale Road intersection next week. Once the intersection tie-in is completed, the pipeline will be filled with natural gas, and crews will begin connecting existing customer service lines to the main.
All potholing excavation work to locate existing utilities has been completed on Corteland Drive, between Bennington Drive and Sheffield Drive. There are two short sections of pipe to bore on Bennington Drive next week, then the crew will move to begin boring work on Corteland Drive.
As a reminder, this project is scheduled to be completed in four zones over the next 18-24 months. Please see the Project Information Sheet & Map in the column to the right for more details related to this project.
This work may require temporary lane closures in the immediate work zone. Motorists and residents are also reminded to watch for the presence of workers, equipment, and vehicles in the area.
KUB will post weekly updates on this blog for the duration of the project.