November 17, 2017 West Hills Area Natural Gas Main Replacement Project Update – This past week, KUB Underground Construction Crews (UGC) continued tie-up work to connect sections of newly installed natural gas main on Sheffield Drive.
Crews will resume tie-up work on Vanosdale Road next week, and then proceed to connecting customer service lines on Bennington Drive and Sheffield Drive.
Crews will not work next Thursday and Friday, November 23-24, due to the Thanksgiving holiday. Work will resume on Monday, November 27.
As a reminder, this project is scheduled to be completed in four zones over the next 18-24 months. Please see the Project Information Sheet & Map in the column to the right for more details related to this project.
This work may require temporary lane closures in the immediate work zone. Motorists and residents are also reminded to watch for the presence of workers, equipment, and vehicles in the area.
KUB will post weekly updates on this blog for the duration of the project.