Crews will begin connecting customer service lines to the new main on Bennington Drive next week.
A second KUB crew worked to bore in sections of new natural main on Corteland Drive this week, and they are scheduled to resume work in that area again next week.
As a reminder, this project is scheduled to be completed in four zones over the next 18-24 months. Please see the Project Information Sheet & Map in the column to the right for more details related to this project.
This work may require temporary lane closures in the immediate work zone. Motorists and residents are also reminded to watch for the presence of workers, equipment, and vehicles in the area.
KUB will post weekly updates on this blog for the duration of the project.
No comments:
Post a Comment