Friday, December 15, 2017

Depot Avenue Water Line Project

NEWS RELEASE

December 15, 2017
For Immediate Release      
                                 
For more Information, contact:
KUB Communications

Depot Avenue Area Water Transmission Line Project to Start Next Week
Excavation to Begin in Blackstock Avenue Area

KUB and its contractor, Garney Construction, are scheduled to begin a project to install 8,500 feet of new 36-inch transmission water main on Monday, December 18, 2018. Construction will begin on Blackstock Avenue and progress north then east toward the project end at East Summit Hill Drive. The entire project is scheduled for completion by May 2019.

In addition to the new 36-inch main, the $6.4 million project includes replacement of aging 1,400 feet of 8-, 12-, and 16-inch distribution water mains in sections along the same route.

Installation of the new 36-inch main will improve reliability and operational flexibility in delivering water from KUB’s Mark B. Whitaker Water Treatment Plant to the west side of the distribution system.

This project will be completed in block-to-block sections. The entire length of the project will not be impacted at the same time; however, two or more locations may be constructed simultaneously.

As excavation begins, Garney Construction will close a short section of Blackstock Avenue between the Western Avenue overpass and Hannah Street from 7 a.m. Monday, December 18, through Thursday, December 21. Alternate routes include Western Avenue, Broadway, and Oak Avenue.

Road, lane, and sidewalk closures will be required during the course of this project to facilitate safe access for equipment and workers. KUB will coordinate all closures and detours with the City of Knoxville. Alternate access will be provided for businesses and parking facilities. KUB and Garney Construction will also coordinate construction schedules to minimize the impact on special events in the area.

Construction methods will include open-cut replacement, as well as trenchless construction methods. Weekday work hours will be limited to generally daylight hours; however, some night and weekend work may be required to meet project milestone dates.

KUB will post regular updates throughout the project on its website at www.kub.org, and on social media. Additionally, KUB has set up a blog at http://kubmajorprojects.blogspot.com to keep customers informed about project milestones. Customers can call 558-2331 after normal business hours to leave a message that will be followed-up with a call from a KUB representative by the end of the next business day.

Depot Avenue Area Map: See right side of blog.

KUB, a municipal utility serving Knox and parts of seven adjacent counties, provides reliable electric, gas, water, and wastewater services to more than 453,000 customers.
###

(North Knoxville) Blackstock Avenue Road Closure [December 18-21] – KUB contract crews will close a short section of Blackstock Avenue between the Western Avenue overpass and Hannah Street from 7 a.m., Monday, December 18, through 5 p.m., Thursday, December 21, as work is performed on the water distribution system in the area. Alternate routes include Western Avenue, Broadway, and Oak Avenue. Access to local businesses will be maintained, and flaggers and signs will be on site to assist with traffic control. Following this work, the roadway will reopen and remain open through the Christmas and New Year’s holidays. Crews are expected to return to this area in early January.  


8 comments:

  1. Delegates are the fundamental need of any industry yet when you are being developed industry constantly endeavor that you should enhance agents it ought to be conceivable from various perspectives like get a couple of specialists or some high paid workers and some proficient one. https://www.alumlight.co.il/

    ReplyDelete
  2. I have visited to this site multiple times and everytime I find beneficial jobs for me so I would suggest please come to this site and take the chance from here. construction project management consulting firms Birmingham

    ReplyDelete
  3. I have visited to this site multiple times and everytime I find beneficial jobs for me so I would suggest please come to this site and take the chance from here. construction project management consulting Manchester

    ReplyDelete
  4. It proved to be Very helpful to me and I am sure to all the commentators here! Chape

    ReplyDelete
  5. Thanks for your insight for your fantastic posting. I’m glad I have taken the time to see this. Georgetown crane rental

    ReplyDelete
  6. Pretty good post. I have just stumbled upon your blog and enjoyed reading your blog posts very much. I am looking for new posts to get more precious info. Big thanks for the useful info. brick pointing contractor New York

    ReplyDelete
  7. Easily, the article is actually the best topic on this registry related issue. I fit in with your conclusions and will eagerly look forward to your next updates. stamped concrete cracks

    ReplyDelete
  8. Such a very useful article. Very interesting to read this article.I would like to thank you for the efforts you had made for writing this awesome article. stamped concrete cracks

    ReplyDelete