May 10, 2019 UPDATE – Construction crews will
work in the following areas next week with daily road closures between 7 a.m. –
5 p.m.:
- Bluff View Road between Scenic Drive and Holloway Drive
(construction in this area also includes work in nearby off-road
easements)
Construction crews will
also work on the following roads with intermittent lane closures
between 7 a.m. – 5 p.m.:
- Cherokee Boulevard between Tugaloo Drive
and Kenesaw Avenue (southbound lane closed during daytime work hours with
traffic flow detoured via Tugaloo Drive, Taliluna Avenue, and Kenesaw
Avenue)
- Northbound traffic flow on this
stretch of Cherokee Boulevard and Sequoyah Greenway will remain open at
all times
- Beacon Hill Lane
Concrete Restoration – Crews will also work on short sections of the following roads
requiring 24-hour road closures. The 24-hour time frame includes crews
setting up forms, pouring and finishing concrete, time for concrete to cure
overnight, and removal of forms the following day. Access to driveways will be
maintained. Work on these roads will be scheduled so that all roads are not
closed at the same time:
- Windgate Street
between Oakhurst Drive and Iskagna Drive
- W. Nokomis Circle between
Iskagna Drive and E. Nokomis Circle
- E. Nokomis Circle between
Iskagna Drive and W. Nokomis Circle
Closed-circuit Television
Inspection – Crews will continue to
work throughout the Phase 2 area next week. Temporary lane closures will be
implemented as needed when crews are present.
Sequoyah Park – Morgan Construction and their subcontractors continue to
rehabilitate the existing wastewater main and manholes in Sequoyah Park. See
the attached map showing current work corridors within the park. The park, all
entrances and parking areas, and boat ramp remain open during this work. Morgan
Construction is also maintaining a fenced area in the middle parking lot for
equipment and materials storage. KUB has coordinated work in the park with City
of Knoxville Parks and Recreation and the Kingston Pike Sequoyah Hills
Association. Informational banners have been placed in the park
entrances/parking areas to provide park visitors with details about the
wastewater rehabilitation work. Updates on the progress of work in the park
will be posted weekly and as needed on this blog site.
Natural
Gas System Work – KUB Underground Construction crews will be working to replace
selected natural gas valves and customer service lines on short sections of
Cherokee Boulevard, Scenic Drive, Windgate Street, Iskagna Drive, Kenesaw
Avenue, Navaho Road SW, W. Nokomis Circle, Keowee Avenue, Taliluna Avenue,
Bluff View Road SW, Cedarhill Road SW, E. Nokomis Circle, Woodland Drive, and
Sequoyah Avenue over the next several months. Temporary natural gas customer
outages may be needed in the immediate area where crews are working to safely
facilitate this work. KUB Customer Support will notify all affected customers
in advance of any planned outage. Additionally, temporary lane closures may be
needed in association with this work.