May 17, 2019 UPDATE –
see maps to the right for corresponding work zones:
Construction crews will work in the following areas next week
with daily road closures between 7 a.m. – 5 p.m.:
- Holloway
Drive between Bluff View Drive and Cedarhill Road (construction in this
area also includes work in nearby off-road easements)
- Cherokee
Boulevard between Tugaloo Drive and Kenesaw Avenue (southbound lane closed
during daytime work hours with traffic flow detoured via Tugaloo Drive,
Taliluna Avenue, and Kenesaw Avenue)
- Northbound
traffic flow on this stretch of Cherokee Boulevard and Sequoyah Greenway
will remain open at all times
·
Bluff View Drive (paving
and restoration)
·
Beacon Hill Lane (paving and restoration)
·
W. Nokomis Circle (paving and restoration near Keowee Avenue intersection)
Concrete
Restoration –
Crews will also work on concrete restoration on short sections of the following
roads requiring 24-hour road closures. The 24-hour time frame includes
crews setting up forms, pouring and finishing concrete, time for concrete to
cure overnight, and removal of forms the following day. Access to driveways
will be maintained. Work on these roads will be scheduled so that all roads are
not closed at the same time:
- Windgate Street between Oakhurst Drive and Iskagna Drive
- W.
Nokomis Circle between Iskagna Drive and E. Nokomis Circle
- E.
Nokomis Circle between Iskagna Drive and W. Nokomis Circle
- Iskagna
Drive between Kenesaw Avenue and Woodside Street
Vegetation Management – KUB contract tree pruning
crews will also work in the Bluff View Drive and Holloway Drive area the week
of May 20-24. Completion of vegetation work in coordination with ongoing
wastewater work will minimize the need for another disruption and access to
back and side lots in the near future. Temporary lane closures may be needed in the immediate
area where crews are working.
Closed-circuit
Television Inspection – Crews will continue to work throughout the Phase 2 area next
week. Temporary lane closures will be implemented as needed when crews are
present.
Sequoyah
Park –
Morgan Construction and their subcontractors continue to rehabilitate the
existing wastewater main and manholes in Sequoyah Park. See the attached map
showing current work corridors within the park. The park, all entrances and
parking areas, and boat ramp remain open during this work. Morgan Construction
is also maintaining a fenced area in the middle parking lot for equipment and
materials storage. KUB has coordinated work in the park with City of Knoxville
Parks and Recreation and the Kingston Pike Sequoyah Hills Association.
Informational banners have been placed in the park entrances/parking areas to
provide park visitors with details about the wastewater rehabilitation work.
Updates on the progress of work in the park will be posted weekly and as needed
on this blog site.
Natural
Gas System Work – KUB Underground Construction crews will be working to replace
selected natural gas valves and customer service lines on short sections of
Cherokee Boulevard, Scenic Drive, Windgate Street, Iskagna Drive, Kenesaw
Avenue, Navaho Road SW, W. Nokomis Circle, Keowee Avenue, Taliluna Avenue,
Bluff View Road SW, Cedarhill Road SW, E. Nokomis Circle, Woodland Drive, and
Sequoyah Avenue over the next several months. Temporary natural gas customer
outages may be needed in the immediate area where crews are working to safely
facilitate this work. KUB Customer Support will notify all affected customers
in advance of any planned outage. Additionally, temporary lane closures may be
needed in association with this work. Cherokee Boulevard Work Week
of May 20-24: A valve replacement crew is scheduled to work in the
grass median on Cherokee Boulevard near the Tugaloo Drive intersection. The
Sequoyah Greenway will remain open with a temporary trail diversion in the
immediate area where the crew is working.