Friday, August 23, 2019

Holston Hills Natural Gas Project

August 23, 2019 Update –Contractor East Tennessee Pipeline crews finished up boring in new natural gas pipeline between the 5400 and 5500 blocks on Crestwood Drive this week. Next week, the contractor will work on service line tie-ins starting at 5908 E. Sunset Road and progressing toward the 5500 block, tying in sections of natural gas main on Farragut Drive at Holston Hills Drive and Crestwood Drive, and potholing to locate existing underground utilities and boring on Holston Hills Drive from Farragut Drive to Cliffside Lane. 