Friday, November 8, 2019

Fountain City Natural Gas Project


November 8, 2019 – Contractor Classic City Mechanical will work in the following areas next week:
·         Connecting sections of bored-in natural gas main on Grove Drive from Medlin Heights Road to Gresham Road
·         Potholing to located existing buried utility lines and boring in new sections of natural gas main in the following areas:
o   2931 Walkup Drive to Cub Lane
o   Edonia Drive from Weems Road to Ridgewood Road
o   Ridgewood Road from Oak Road to N. Broadway
·         Customer service line connections to the new natural gas main in the following areas:
o   1910 & 1911 Martha Berry Drive
o   6371 – 5941 Grove Drive

No comments: