November
15, 2019 – Testing
was completed successfully on the newly installed water main along Old Kingston
Pike this past week and KUB Underground Construction crews have started
connecting customer service lines to the new water main. KUB crews are
working with customers on an individual basis to schedule each service
tie-over, with some work occurring at night and in the early morning hours to
accommodate customers’ needs. Service line work will continue for the
next 1-2 weeks. KUB crews plan to complete the water main installation
along S. Forest Park Boulevard next week with testing and service line connections
to occur in the days and weeks following. Road and lane closures will be
implemented on S. Forest Park Boulevard as needed to facilitate this work.
Access to businesses will be maintained. KUB contract paving crews are actively
patching the excavation areas along Old Kingston Pike and Staub Street.
Water main replacement is scheduled to last through early January 2020 in this
area. To minimize future disruptions in this area, KUB will follow the water
main project with wastewater collection system upgrades in this same area
starting in early January. Final paving and restoration will take place at the
conclusion of the wastewater project.