Boring crews have completed installation of in the new main on Bennington Drive. Crews will finish up work on Bennington Drive over the next several weeks by connecting customers’ service lines and connecting sections of main to make it active.
Boring crews were scheduled to continue work on Sheffield Drive to finish out this week before moving over to Corteland Drive to work on the section between Sheffield Drive and Bennington Drive early next week.
As a reminder, this project is scheduled to be completed in four zones over the next 18-24 months. Please see the Project Information Sheet & Map in the column to the right for more details related to this project.
This work may require temporary lane closures in the immediate work zone. Motorists and residents are also reminded to watch for the presence of workers, equipment, and vehicles in the area.
KUB will post weekly updates on this blog for the duration of the project.
KUB Underground Construction crews perform “potholing” excavation work to locate existing underground utilities this past week in the 7800 block of Sheffield Drive.
West hill area natural gas project is popular now a days and this project is to vital in terms of the hydrological process and it should be completed on time.http://www.alumlight.co.il/
ReplyDelete