September 8, 2017 West Hills Area Natural Gas Main Replacement Project Update – Crews are scheduled to bore approximately 450 feet of new natural gas main in the 7600 block of Sheffield Drive on Friday, September 8, and will continue work on Sheffield Drive next week.
Additionally, crews will be digging to locate existing utilities (potholing) next week on Sheffield Drive, south of Bennington Drive.
Tie-up crews will begin connecting sections of main on Bennington Drive by the last week of September.
As a reminder, this project is scheduled to be completed in four zones over the next 18-24 months. Please see the Project Information Sheet & Map in the column to the right for more details related to this project.
This work may require temporary lane closures in the immediate work zone. Motorists and residents are also reminded to watch for the presence of workers, equipment, and vehicles in the area.
KUB will post weekly updates on this blog for the duration of the project.