February 15, 2019 UPDATE – Noelton Drive Water Main Replacement Project – KUB
Underground Construction crews continued work to connect customer service lines
to the new main on Noelton Drive. Crews also performed paving and restoration
work as weather conditions allowed. Weather conditions have also delayed the
start of water main replacement work on Chippewa Circle and
Dogwood Lane. Construction will start on those streets as conditions allow.
The
above-mentioned streets will remain closed to through traffic for the duration
of this project, which is scheduled for completion in February 2019. See map
for installation areas. Flaggers, signs, and other necessary traffic control
measures will be in place in association with these closures.
Wastewater
Rehabilitation Phase 1 – Contractor crews
continue closed-circuit TV inspections of wastewater system pipes and manhole
repairs requiring intermittent lane closures between 7 a.m. and 5 p.m. on
Arrowhead Trail (between Lyons View Pike and Blows Ferry Road) through February
22, 2019. Mellen Avenue will serve as an alternate route. Pipe lining crews
finished work on Towanda Trail and in an off-road easement east of Kingston
Park Drive this past week. Work also continues in an off-road easement near the
intersection of Blows Ferry Road and Alta Vista Way through February 22. See
attached map.
Wastewater
Rehabilitation Phase 2 – Pre-construction
activities, including closed-circuit TV inspections of existing wastewater
pipes and manholes, continue in the Phase 2 work area of Sequoyah Hills as
weather allows. There may be temporary intermittent lane closures on area roads
as vehicles and equipment associated with the inspection work are present. Full
construction activity requiring longer lane and road closures will begin in
weeks following. Customers can continue to monitor the progress of work in
Phase 2, including information on active work zones and traffic impacts, via
this blog. Additionally, customers throughout Sequoyah Hills will receive
notice by mail prior to the start of construction activities. See the attached
Sequoyah Hills construction phases map.
(Sequoyah Hills) Arrowhead Trail
Road Closure [February 18-22] – KUB contract crews will close
Arrowhead Trail
between Lyons View Pike and Blows Ferry Road to through traffic from 7 a.m. – 5 p.m., from February
18-22, as work is performed on the wastewater collection systems in the area.
Access to driveways will be maintained, and the road will reopen to normal
traffic flow when construction crews are not present. Appropriate signage and
barricades will be on site to assist with traffic control. Follow-up advisories
will be issued as necessary.