February 22, 2019 UPDATE – Noelton Drive Water Main
Replacement Project – KUB Underground Construction crews completed
installation and testing of the new water main on Chippewa Circle this week. Crews
will shift the work zone to Dogwood Lane next week. Customer service line
connections remain on Chippewa Circle. Paving and restoration work will
continue in these areas as weather conditions allow.
The above-mentioned
streets will remain closed to through traffic for the duration of this project,
which is scheduled for completion in early March 2019. See map for installation
areas. Flaggers, signs, and other necessary traffic control measures will be in
place in association with these closures.
Sequoyah Hills
Wastewater Rehabilitation Phase 1 – Contractor crews
continue closed-circuit TV inspections of wastewater system pipes and manhole
repairs requiring intermittent lane closures as weather allows between 7 a.m.
and 5 p.m. on Arrowhead Trail (between Lyons View Pike and Blows Ferry Road)
through March 1, 2019. Mellen Avenue will serve as an alternate route. Pipe
lining crews finished work in an off-road easement near the intersection of
Blows Ferry Road and Alta Vista Way. See attached map.
Sequoyah Hills
Wastewater Rehabilitation Phase 2 – KUB and its contractor,
Morgan Construction, are scheduled to begin construction activity in the
northern sections of Phase 2 on Monday, March 4. Portions of Phase 2 construction take place in Sequoyah Park and along
Cherokee Boulevard/Sequoyah Greenway later this spring. KUB and the contractor
will coordinate all work in those areas with the City of Knoxville. Sequoyah
Park will remain open for use at all times with construction zones isolated by
barriers. All impacts related to work in those areas will be communicated well
in advance. KUB will also coordinate with the appropriate agencies to avoid
conflicts with the Knoxville Marathon and Dogwood Trails in the area this
spring. Customers
can continue to monitor the progress of work in Phase 2, including information
on active work zones and traffic impacts, via this blog. Additionally,
customers throughout Sequoyah Hills will receive notice about Phase 2 by mail
soon. See the attached Sequoyah Hills construction phases map.
KUB has
designated the two Utility Service Advisors as the customer contacts for this
project (contact weekdays between 7 a.m. – 4 p.m.):
·
Tim Cox – (865) 558-2947 [office] or
313-3777 [cell]
·
Tom England – (865)
558-2177 [office] or 640-3157[cell]
(Sequoyah Hills Area) Arrowhead Trail Road Closure [February
24-28] –
KUB contract crews will close Arrowhead Trail between Lyons View Pike and Blows
Ferry Road to through traffic from 7 a.m. – 5 p.m.,
from Sunday, February 24, through Thursday, February 28, as work is performed
on the wastewater collection system in the area. Access to driveways will be
maintained, and the road will reopen to normal traffic flow when construction
crews are not present. The road will be closed intermittently during the
regular work hours. Appropriate signage and barricades will be on site to
assist with traffic control. Follow-up advisories will be issued as necessary.