Friday, January 24, 2020
Holston-Chilhowee Area Wastewater Project (Mini-basin 20A3)
January 24, 2020 – KUB’s contractor for this project, Morgan
Construction, is scheduled to begin mobilizing on sections of Silva Drive,
Parva Drive, Iroquois Drive, and Comanche Drive in the area north of Asheville
Highway the week of January 27. As a reminder, due to the location of some
wastewater pipes and manholes under area roadways, temporary lane and/or road
closures may be needed in the immediate area where crews are working for the
duration of this project. This project is scheduled for completion by December
2020. NOTE: The next blog update will be posted on Monday, February 3.
Sequoyah Hills Wastewater Project
January 24, 2020 UPDATE – Construction crews will work in the following areas next week
with intermittent road closures between 7 a.m. – 5 p.m.:
·
Taliluna Avenue between
South Garden Road and Lakeland Drive
·
Whitlow Avenue between
Bluff View Road and Cedarhill Road
Closed-circuit
Television Inspection – Crews will continue to work throughout the Phase 2 area next
week. Temporary lane closures will be implemented as needed when crews are
present.
Manhole
Rehabilitation – Crews will work throughout the Phase 2 area next week. Temporary
lane closures will be implemented as needed when crews are present.
Sequoyah
Park –
Break-down of bypass pumping equipment and piping is complete. Cleanup and
restoration of disturbed areas will continue as weather allows over the next
several weeks. See the attached map showing current work corridors within the
park. The park, all entrances and parking areas, and boat ramp remain open
during this work. Morgan Construction continues to maintain a fenced area in
the middle parking lot for equipment and materials storage. KUB has coordinated
work in the park with City of Knoxville Parks and Recreation and the Kingston
Pike Sequoyah Hills Association. Informational banners have been placed in the
park entrances/parking areas to provide park visitors with details about the
wastewater rehabilitation work. Updates on the progress of work in the park
will be posted weekly and as needed on this blog site.
Natural
Gas System Work – Crews are scheduled to resume natural gas inspection and
maintenance work at various locations throughout Sequoyah Hills in February.
This work may require short term traffic impacts in the immediate area where
crews are working.
NOTE: The next blog update will be posted on
Monday, February 3.
Holston Hills Natural Gas Project
January 24, 2020 Update –Contractor
East Tennessee Pipeline crews will work in the following areas next week:
-
1212, 1300 S. Chilhowee Drive
-
5107, 5111, 5121 Green Valley Drive
-
5115 Wyndcroft Drive
-
4815 Shady Dell Trail
-
1120, 1124, 1125 Montview Road
-
4703, 4706, 4801, 4804, 4812, 4900
Westover Terrace
NOTE: The next blog update will be posted on
Monday, February 3.
Fountain City Natural Gas Project
January 24, 2020
– Contractor Classic City Mechanical will work in the following areas next
week:
·
o
6136, 6141 Weems Road
o
5617, 5628, 5720 Ridgewood Road
o
3004-3116 Edonia Drive
o
2813, 2822 Pruden Drive
o
5900 Van Horn Road
o
5924 & 6024 Grove Drive
NOTE: The next blog update will be posted on
Monday, February 3.
Old Kingston Pike Area Wastewater Project
January
24, 2020 – KUB’s
contractor for this project, Hurst Excavating, is scheduled to begin
mobilization and pre-construction activities in the area the week of January
27. As a reminder, due to the location of some wastewater pipes and manholes
under the roadway, temporary lane and/or road closures may be needed in the
immediate area where crews are working for the duration of this project. This
project is scheduled for completion by late April 2020. Final overall paving
and restoration will take place at the conclusion of the wastewater project. NOTE:
The next blog update will be posted on Monday, February 3.
Concord Street Wastewater Project
January 24, 2020 – KUB’s contractor, Morgan Construction, is
scheduled to begin mobilization the week of January 27. As a reminder, due to the
location of wastewater pipes and manholes under the roadway, lane shifts will
be needed in the immediate area where crews are working for the duration of
this project. This project is scheduled for completion by late March 2020.
NOTE: The next blog update will be posted on Monday, February 3.
South Knoxville Water & Wastewater Project (Mini-basin 40C1)
January 24, 2020 – KUB’s contractor, Portland Utilities, continued
installing sections of new water main on Boggs Avenue this past week. Crews
will continue work from east to west on Boggs Avenue with daily road closures
in the immediate work zone daily from 7:30 a.m. – 6 p.m. next week. Crews are
also scheduled to start saw-cutting roadway asphalt and installing water main
on the section of Davenport Road between Boggs Avenue and Kingland Avenue next
week. This work will require daily road closures between 9 a.m. – 3 p.m. Access
to driveways will be maintained. NOTE: The next blog update will be
posted on Monday, February 3.
Tuesday, January 21, 2020
Old Kingston Pike Wastewater Rehabilitation Project
January 21, 2020 -
Beginning the week of January 20, 2020, KUB and its contractor will begin mobilizing equipment and materials for a Century II wastewater collection system rehabilitation project in the Old Kingston Pike area. This project will upgrade approximately 3,300 linear feet of existing wastewater pipeline and 13 manholes in the area. Construction methods include open-cut trenching, pipe-bursting, and lining of existing pipe. Note that a temporary odor will be present in the immediate area in association with the lining process. Due to the location of some sections of pipe and manholes under roadways, temporary lane and/or road closures will be needed in the immediate area(s) where crews are working. Access to driveways will be maintained. Additionally, crews may need to access buried pipes and manholes in off-road easements. Lawn and street restoration will follow once construction is completed and as weather conditions allow. Follow-up notices will be issued as needed for the duration of this project. See attached map.
Beginning the week of January 20, 2020, KUB and its contractor will begin mobilizing equipment and materials for a Century II wastewater collection system rehabilitation project in the Old Kingston Pike area. This project will upgrade approximately 3,300 linear feet of existing wastewater pipeline and 13 manholes in the area. Construction methods include open-cut trenching, pipe-bursting, and lining of existing pipe. Note that a temporary odor will be present in the immediate area in association with the lining process. Due to the location of some sections of pipe and manholes under roadways, temporary lane and/or road closures will be needed in the immediate area(s) where crews are working. Access to driveways will be maintained. Additionally, crews may need to access buried pipes and manholes in off-road easements. Lawn and street restoration will follow once construction is completed and as weather conditions allow. Follow-up notices will be issued as needed for the duration of this project. See attached map.
Holston-Chilhowee Area Wastewater Rehabilitation Project (Loves Creek/Mini-Basin 20A3)
January 21, 2020 -
Beginning the
week of January 20, 2020, KUB and its contractor will begin mobilizing
equipment and materials for a Century II wastewater collection system
rehabilitation project in the Holston-Chilhowee area. This project will upgrade
approximately 20,00 linear feet of existing wastewater pipeline and 41 manholes
in the area. Construction methods include open-cut trenching, pipe-bursting,
and lining of existing pipe. Note that a temporary odor will be present in the
immediate area in association with the lining process. Due to the location of
some sections of pipe and manholes under roadways, temporary lane and/or road
closures will be needed in the immediate area(s) where crews are working. Access
to driveways will be maintained. Additionally, crews may need to access buried
pipes and manholes in off-road easements. Lawn and street restoration will
follow once construction is completed, as weather conditions allow. Follow-up
notices will be issued as needed for the duration of this project. See attached
map.
Friday, January 17, 2020
Farragut Hills Boulevard Natural Gas Project
January
17, 2020 –
Construction notice postcards were mailed to customers in the Farragut Hills
Boulevard area earlier this week. This project is scheduled to begin in early
February, with completion set for late April 2020. Look for weekly updates once
construction begins.
South Knoxville Water & Wastewater Project (Mini-basin 40C1)
January
17, 2020 – KUB’s
contractor, Portland Utilities, began installing sections of new water main on
Boggs Avenue this past week. Crews will continue work west on Boggs Avenue with
daily road closures in the immediate work zone daily from 7:30 a.m. – 6 p.m.
next week. Crews are also scheduled to start saw-cutting roadway asphalt and
installing water main on the section of Davenport Road between Boggs Avenue and
Kingland Avenue next week. This work will require daily road closures between 9
a.m. – 3 p.m. Access to driveways will be maintained.
Concord Street Wastewater Project
January
17, 2020 – KUB’s
contractor, Morgan Construction, is scheduled to begin mobilization the week of
January 27. As a reminder, due to the location of wastewater pipes and manholes
under the roadway, temporary lane shifts will be needed in the immediate area
where crews for the duration of this project. This project is scheduled for
completion by late March 2020.
Holston-Chilhowee Area Wastewater Project (Mini-basin 20A3)
January
17, 2020 – KUB’s
contractor for this project, Morgan Construction, is scheduled to begin
mobilization and pre-construction activities the week of January 20. As a
reminder, due to the location of some wastewater pipes and manholes under area
roadways, temporary lane and/or road closures may be needed in the immediate
area where crews are working for the duration of this project. This project is
scheduled for completion by December 2020.
Old Kingston Pike Wastewater Project
January 17, 2020 – Construction notice postcards were mailed to
customers in the Old Kingston Pike earlier this week. KUB’s contractor for this
project, Hurst Excavating, is scheduled to begin mobilization and
pre-construction activities in the area the week of January 20. As a reminder,
due to the location of some wastewater pipes and manholes under the roadway,
temporary lane and/or road closures may be needed in the immediate area where
crews are working for the duration of this project. This project is scheduled
for completion by late April 2020. Final overall paving and restoration will
take place at the conclusion of the wastewater project.
Fountain City Natural Gas Project
January 17, 2020
– Contractor Classic City Mechanical will work in the following areas next
week:
- Customer service line
connections to the new natural gas mains in the following areas:
- 6141 Weems Road
- 5617, 5628, 5720 Ridgewood
Road
- 3004-3116 Edonia Drive
- 2901-2949 Walkup Drive
- 5900 Van Horn Road
Holston Hills Natural Gas Project
January 17, 2020 Update – Contractor
East Tennessee Pipeline crews will work in the following areas next week:
- Customer service line
connections to the new natural gas main in the following areas:
- 1212, 1300 S. Chilhowee Drive
- 5107, 5109, 5111, 5115, 5119,
5121, 5125 Green Valley Drive
- 5111, 5115 Wyndcroft Drive
Sequoyah Hills Wastewater Project
January 17, 2020 UPDATE - Construction crews will work in the following areas next week
with intermittent road closures between 7 a.m. – 5 p.m.:
- Taliluna
Avenue between South Garden Road and Lakeland Drive
- Whitlow Avenue between Bluff View Road and Cedarhill Road
Closed-circuit
Television Inspection – Crews will continue to work throughout the Phase 2 area next
week. Temporary lane closures will be implemented as needed when crews are
present.
Manhole
Rehabilitation – Crews will work throughout the Phase 2 area next week.
Temporary lane closures will be implemented as needed when crews are present.
Sequoyah
Park –
Break-down of bypass pumping equipment and piping is nearing completion in the
park. Cleanup and restoration of excavated areas will continue as weather
allows over the next several weeks. See the attached map showing current work
corridors within the park. The park, all entrances and parking areas, and boat
ramp remain open during this work. Morgan Construction continues to maintain a
fenced area in the middle parking lot for equipment and materials storage. KUB
has coordinated work in the park with City of Knoxville Parks and Recreation
and the Kingston Pike Sequoyah Hills Association. Informational banners have
been placed in the park entrances/parking areas to provide park visitors with
details about the wastewater rehabilitation work. Updates on the progress of
work in the park will be posted weekly and as needed on this blog site.
Natural
Gas System Work – Crews are scheduled to resume natural gas inspection and
maintenance work at various locations throughout Sequoyah Hills in February.
This work may require short term traffic impacts in the immediate area where
crews are working.