South Knoxville Water & Wastewater Project (Mini-basin 40C1)
January 24, 2020 – KUB’s contractor, Portland Utilities, continued
installing sections of new water main on Boggs Avenue this past week. Crews
will continue work from east to west on Boggs Avenue with daily road closures
in the immediate work zone daily from 7:30 a.m. – 6 p.m. next week. Crews are
also scheduled to start saw-cutting roadway asphalt and installing water main
on the section of Davenport Road between Boggs Avenue and Kingland Avenue next
week. This work will require daily road closures between 9 a.m. – 3 p.m. Access
to driveways will be maintained. NOTE: The next blog update will be
posted on Monday, February 3.