Friday, January 17, 2020

South Knoxville Water & Wastewater Project (Mini-basin 40C1)

January 17, 2020 – KUB’s contractor, Portland Utilities, began installing sections of new water main on Boggs Avenue this past week. Crews will continue work west on Boggs Avenue with daily road closures in the immediate work zone daily from 7:30 a.m. – 6 p.m. next week. Crews are also scheduled to start saw-cutting roadway asphalt and installing water main on the section of Davenport Road between Boggs Avenue and Kingland Avenue next week. This work will require daily road closures between 9 a.m. – 3 p.m. Access to driveways will be maintained.