Old Kingston Pike Water Main Project

January 3, 2020 – KUB Underground Construction crews have completed the installation of all new water mains and customer service line connections along Old Kingston Pike, Staub St and S. Forest Park Blvd. No work will be performed in this area until early January 2020. To minimize future disruptions in this area, KUB will follow the water main project with wastewater collection system upgrades in this same area starting in January 2020. Affected customers will be notified prior to the start of wastewater construction. Final overall paving and restoration will take place at the conclusion of the wastewater project.