Friday, January 5, 2018

Depot Avenue Water Line Project

January 5, 2018 Depot Avenue Water Transmission Line Project Update - KUB contract crews will implement the below traffic control plan as work continues on this project: 

(North Knoxville) Blackstock Avenue Road Closure [January 8-12] – KUB contract crews will close a short section of Blackstock Avenue between the Western Avenue overpass and Hannah Street from 7 a.m., January 8, through 5 p.m., Friday, January 12, as work is performed on the water distribution system in the area. Alternate routes include Western Avenue, Broadway, and Oak Avenue. Access to local businesses will be maintained, and flaggers and signs will be on site to assist with traffic control. 

No comments:

Post a Comment