Sequoyah Hills Area Wastewater Rehabilitation Project

January 5, 2018 UPDATE - KUB and its contractor, Hurst Excavating, are scheduled to begin pre-construction activity in the Phase 1 project area on Monday, January 8.

This work will include subcontractors conducting closed-circuit camera inspections of wastewater pipes and manholes. Workers will also be present in the area to identify and mark existing underground utility lines in construction zones with paint and/or flags.

Digging work is expected to begin on Monday, January 29, in the Scenic Drive area near the Kingston Pike intersection. Once construction excavation begins, work will progress south on Scenic Drive and Southgate Road. Phase 1 is expected to last approximately one year.