April 6, 2018 UPDATE – Garney Construction pipe installation crews continued installation of a 12-inch water main on the section of W. Fifth Avenue between Cooper Street and N. Broadway. This section of road will remain closed through mid-April. Crews also dug two pits and began setting up bore equipment in the two-block section of Morgan Street between E. Depot Avenue and E. Jackson Avenue for pipe installation under railroad tracks in this area. This section of Morgan Street will be closed through the end of April 2018. Boring crews continue to work on installation of sections of pipe under the railroad tracks in the area beneath the W. Fifth Avenue bridge to the west of Cooper Street. Work Zone Shift Update: Beginning on Tuesday, April 10, Garney Construction is expected to close the N. Broadway at N. Central Street intersection for pipe installation. This closure is expected to remain in place through April 20. Alternate routes around this work zone include W. Depot Avenue, W. Magnolia Avenue, N. Gay Street, Fifth Avenue, Bernard Avenue, and Cooper Street. KUB and Garney Construction will communicate details related to the intersection closure in advance. KUB and Garney Construction will have the work zone on Morgan Street blocked off to avoid conflicts with the Rhythm n Blooms Music Festival in the Old City this weekend.
(North Knoxville) N. Broadway Lane Closures [April 9-11] – KUB crews will close the southbound, curbside lane of N. Broadway between Central Street and Tyson Street from 9 a.m. – 3 p.m. daily, starting Monday, April 9, through Wednesday, April 11, as work is performed on the natural gas distribution system in the area. One southbound lane and both northbound lanes will remain open. Access to local businesses will be maintained, and flaggers and signs will be on site to assist with traffic control.
(North Knoxville) N. Broadway and W. Fifth Avenue Intersection Closure [April 10-20] – KUB contract crews will close the N. Broadway and W. Fifth Avenue intersection starting at 7 a.m., Tuesday, April 10, through 5 p.m. Friday, April 20, as work is performed on the water distribution system in the area. As part of this closure, the below sections of roadway will also be closed:
· W. Fifth Avenue between Queen Street and N. Broadway
· W. Fifth Avenue between N. Gay Street and N. Broadway
Alternate routes include W. Depot Avenue, W. Magnolia Avenue, N. Gay Street, and Fifth Avenue, Bernard Avenue, and Cooper Street. This work has been coordinated with the City of Knoxville, and motorists are reminded of ongoing work in the N. Broadway and Central Street intersection. Access to local driveways will be maintained, and flaggers and signs will be on site to assist with traffic control. Follow-up advisories will be issued as necessary.
No comments:
Post a Comment