April 20,
2018 UPDATE – Hurst Excavating subcontractor crews finished digging work on
Mellen Avenue this past week. Paving and restoration crews will implement
intermittent daily road closures along Mellen Avenue through the end of next
week. Restoration work was completed in the off-road easements along back and
side property lines between Scenic Drive and Valencia Road (parallel to Alta
Vista Way). Sewer pipeline rehabilitation work was also completed on Keowee
Avenue, the lower portion of Southgate Road, and Wilani Road this past week.
Paving and restoration crews will work on those areas through the end of next
week. Looking ahead to next week, construction crews will work in an off-road
easement at the intersection of Oakhurst Drive and Woodland Drive, and along
Kenesaw Avenue between Woodland Drive and Wester Wood Avenue through April 27.
A crew is also scheduled to install a manhole on Taliluna Avenue, just west of
the Southgate Drive intersection next week. No work will be performed on any
streets designated as part of the Dogwood Arts Festival Trails and Gardens
through April 30. See attached map for current work zones.
(Sequoyah
Hills Area) Sequoyah Hills Area Road Closures [April 23 – May 4] – KUB contract crews
will implement the below road closures from 7a.m. – 5 p.m. daily, starting
Monday, April 23, through Friday, May 4, as work continues on the wastewater
collections system in the area:
- Taliluna Avenue between Southgate Road and Lakeland Drive
- Woodland Drive between Oakhurst Drive and Kennesaw Avenue
- Keowee Avenue between Woodland and Wester Wood Avenue
No comments:
Post a Comment