West Hills Natural Gas Project

April 27, 2018 UPDATE –  KUB Underground construction crews worked to connect customer service lines on Carrington Road loop west of Marlboro Drive this past week. Crews are scheduled to work on Chadwick Drive (between Corteland Drive and Broome Road), Carrington Road, the 900 block of Marlboro Road, and the 8100 block of Ainsworth Drive next week. This past week, KUB mailed a spring 2018 project update to customers in all four construction zones to advise on the status of the project. Please see the attached updated information sheet and overall project map that was included in the mailing for more details. 