Thursday, April 12, 2018
Sequoyah Hills Wastewater Project
April 12, 2018 UPDATE – Hurst Excavating subcontractor crews finished digging work on the lower section of Southgate Road mid-week. Crews shifted the excavation work zone to Mellen Avenue on Thursday, April 12. Digging work requiring daily road closures is expected to last in this area through early May. Paving and restoration crews will work on the lower end of Southgate Road, Keowee Avenue, Sequoyah Avenue, Taliluna Avenue, and Wilani Road through the end of April. Restoration work also continues in the off-road easements along back and side property lines between Scenic Drive and Valencia Road (parallel to Alta Vista Way) as the contractor waits for favorable surface conditions following recent heavy rains. No work will be performed on any streets designated as part of the Dogwood Arts Festival Trails and Gardens through April 30. See map in the blog side bar for current work zones.