Friday, March 1, 2019

Sequoyah Hills Wastewater Project

March 1, 2019 UPDATE – Noelton Drive Water Main Replacement Project – KUB Underground Construction crews have completed water main installation and testing of the new water main on Chippewa Circle this week. Paving and restoration work continues on Noelton Drive and Chippewa Circle as weather allows. Water main installation crews shifted the work zone to Dogwood Lane this past week. Customer service line connections and paving and restoration work will follow on Dogwood Lane.

The above-mentioned streets will remain closed to through traffic for the duration of this project, which is scheduled for completion in early March 2019. See map for installation areas. Flaggers, signs, and other necessary traffic control measures will be in place in association with these closures.


KUB Underground Construction employees work on Dogwood Lane.



Sequoyah Hills Wastewater Rehabilitation Phase 1 – Contractor crews completed closed-circuit TV inspections of wastewater system pipes and manhole repairs on Arrowhead Trail (between Lyons View Pike and Blows Ferry Road) this past week. Manhole rehabilitation crews will work at various locations throughout the Phase 1 area. Temporary lane closures may be needed in the immediate area where crews are working.

Sequoyah Hills Wastewater Rehabilitation Phase 2 – KUB Phase 2 contractor, Morgan Construction, will begin construction activity with pipe-bursting crews working on short sections of Kenesaw Avenue (between Woodland Drive and Iskagna Drive) and Keowee Avenue (between Southgate Road and West Nokomis Circle) next week. Work in these areas will require daily road closures between 7 a.m. – 5 p.m. Access to driveways will be maintained.

(Sequoyah Hills) Kenesaw Avenue Road Closure [March 4-8] – KUB contract crews will close a short section of Kenesaw Avenue between Woodland Drive and Iskagna Drive to through traffic from 7 a.m.- 5 p.m. daily, starting Monday, March 4, through Friday, March 8, as work is performed on the wastewater collection systems in the area. Alternate routes include Keowee Avenue, Woodside Street, Windgate Street, and Oakhurst Drive. Access to businesses and driveways will be maintained. Appropriate signage and barricades will be on site to assist with traffic control. Follow-up advisories will be issued as necessary.

(Sequoyah Hills) Keowee Avenue Road Closure [March 4-8] – KUB contract crews will close Keowee Avenue between Southgate Road and West Nokomis Circle to through traffic from 7 a.m. – 5 p.m. daily, starting Monday, March 4, through Friday, March 8, as work is performed on the wastewater collection systems in the area. Alternate routes include Sequoyah Avenue, Taliluna Avenue, Wilani Road, and Agawela Avenue. Access to driveways and local businesses will be maintained. Appropriate signage and barricades will be on site to assist with traffic control. Follow-up advisories will be issued as necessary. 