July 26, 2019 – KUB Underground Construction crews have
completed installation of the new water main on the section of Homberg Drive
between Whitaker Drive and progressing south and west to S. Mohican Street.
Crews completed water main replacement on S. Mohican Street. Pending successful
testing of the new water main, crews will shift focus to connecting customer
service lines to the new main on the above-mentioned sections of Homberg Drive
and S. Mohican Street. KUB Customer Support and Underground Construction will
coordinate necessary water service interruptions to minimize impacts as
connections are made. Following the service line connection work, crews will
begin installation of the new water main on the section of Homberg Drive west
of S. Mohican Street next week.

Friday, July 26, 2019
Fountain City Natural Gas Project
July 26, 2019
– Construction progress was temporarily slowed by heavy rains in the region
earlier in the week. Next week, crews will install natural gas main on the
section of Grove Drive between Martha Berry Drive and Mynatt Road. Potholing
work to locate existing underground utilities is scheduled for Mynatt Road and
Grove Drive between Martha Berry Drive east to Colonial Circle.
Holston Hills Natural Gas Project
July 26, 2019 Update – Post construction pipeline cleaning
wrapped up on E. Sunset Road this week. Contractor East Tennessee
Pipeline crews will continue installing natural gas main and making tie-in
connections to existing mains on S. Chilhowee Drive next week. Pending
completion of installation, crews will begin pipeline cleaning work on S.
Chilhowee Drive.
Concord/Painter Avenue Area Wastewater Project
July 26, 2019 Update – Third Creek Greenway Trail Diversion – Wastewater rehabilitation work requiring trail
diversions continues on the section of the Third Creek Greenway just west of S.
Concord Street through July 2019. The Third Creek Greenway remains
open. Trail users are reminded to be aware of the presence of equipment,
vehicles, and workers in the area while this work is completed.
Sequoyah Hills Wastewater Project
July 26, 2019 UPDATE – Sequoyah Hills Wastewater Rehabilitation – Construction crews will
work in the following areas next week with intermittent daily road closures
between 7 a.m. – 5 p.m.:
·
Kenesaw Avenue between
Taliluna Avenue and Cherokee Boulevard
·
Navaho Road between
Scenic Drive and South Garden Road
·
Taliluna Avenue
between South Garden Road and Lakeland Drive
·
Iskagna Drive between
Kenesaw Avenue and Keowee Avenue
Crews will also work on the following roads with intermittent lane
closures between 7 a.m. – 5 p.m.:
·
Cherokee Boulevard
between Southgate Road and Scenic Drive (westbound lane closed during daytime
work hours with traffic flow detoured via Southgate Road, Taliluna Avenue,
South Garden Road, Navaho Road, and Scenic Drive)
-
Eastbound traffic flow
on this stretch of Cherokee Boulevard and Sequoyah Greenway will remain open at
all times
·
Keowee Avenue between
Kenesaw Avenue and Talahi Drive
Crews will also work in the following off-road easements with no
traffic impacts:
·
Easement between
Kenesaw Ave and Woodside Street (Wastewater Rehabilitation)
·
Easement between
Holloway Drive and Whitlow Avenue (Restoration)
·
Easement between
Southgate Drive and Bluff View Road (Restoration)
·
Easement between
Kenesaw Avenue and Agawela Avenue (Restoration)
Closed-circuit Television Inspection – Crews will continue to work
throughout the Phase 2 area next week. Temporary lane closures will be
implemented as needed when crews are present.
Sequoyah Park – Morgan Construction and their subcontractors continue to
rehabilitate the existing wastewater main and manholes in Sequoyah Park. See
the attached map showing current work corridors within the park. The park, all
entrances and parking areas, and boat ramp remain open during this work. Morgan
Construction is also maintaining a fenced area in the middle parking lot for equipment
and materials storage. KUB has coordinated work in the park with City of
Knoxville Parks and Recreation and the Kingston Pike Sequoyah Hills
Association. Informational banners have been placed in the park
entrances/parking areas to provide park visitors with details about the
wastewater rehabilitation work. Updates on the progress of work in the park
will be posted weekly and as needed on this blog site.
Natural Gas System Work – Crews have resumed natural gas
inspection and maintenance work at various locations throughout Sequoyah Hills.
This work may require short term traffic impacts in the immediate area where
crews are working.
Friday, July 19, 2019
Fountain City Natural Gas Project
July
19, 2019 –
Contractor crews are nearing completion of new natural gas main installation
along Martha Berry Drive. Crews will move next to Grove Drive to install a new
main from Martha Berry Drive to Grove Villas Way. Potholing work to locate
existing underground utilities also started on Mynatt Road this week and will
continue on the section of Grove Drive from Martha Berry Drive east to Colonial
Circle. Main installation will continue on Grove Drive next week, starting at
Grove Villas Way and progressing north across Rifle Range Road to 2372 Mynatt
Road.
Homeberg Drive Water Main Project
July 19, 2019 – KUB Underground Construction crews have
installed approximately 1,000 feet of new water main on Homberg Drive, starting
at Whitaker Drive and progressing south and west to S. Mohican Street. Crews
are scheduled to work this weekend to install main and connect to the existing
main on S. Mohican Street. Work will continue on the section of Homberg Drive
west of S. Mohican Street next week.
Holston Hills Natural Gas Project
July 19, 2019 Update
– Contractor East
Tennessee Pipeline crews sleeved in a new 4-inch natural gas main into the
abandoned 6-inch cast iron pipeline along S. Chilhowee Drive, starting at the
Holston Drive intersection and working south. Crews will install remaining new
pipe on S. Chilhowee Drive, to the E. Sunset Road intersection, next week. Post
construction pipeline cleaning work will continue on East Sunset Drive next
week.
Sequoyah Hills Wastewater Project
July 19, 2019 UPDATE – Construction crews will
work in the following areas next week with intermittent daily road closures
between 7 a.m. – 5 p.m.:
·
Kenesaw Avenue between
Woodland Drive and Iskagna Drive (intermittent road
closures as needed for paving and restoration)
·
Keowee Avenue between
Kenesaw Avenue and Talahi Drive
·
Kenesaw Avenue between
Taliluna Avenue and Cherokee Boulevard
Crews will also work on the following roads with intermittent lane
closures between 7 a.m. – 5 p.m.:
·
Cherokee Boulevard
between Southgate Road and Scenic Drive (westbound lane closed during daytime
work hours with traffic flow detoured via Southgate Road, Taliluna Avenue,
South Garden Road, Navaho Road, and Scenic Drive)
-
Eastbound traffic flow
on this stretch of Cherokee Boulevard and Sequoyah Greenway will remain open at
all times
Crews will also work in the following off-road easements with no
traffic impacts:
·
Easement between
Kenesaw Avenue and Woodside Street (Wastewater rehabilitation)
·
Easement between
Holloway Drive and Whitlow Avenue (Wastewater rehabilitation and restoration)
·
Easement between
Kenesaw Avenue and Agawela Avenue (Wastewater rehabilitation)
·
Easement between
Southgate Drive and Bluffview Drive (Restoration)
·
Easement between
Bluffview Road and Southgate Drive (Restoration)
·
Easement between
Keowee Avenue and Talahi Drive (Wastewater restoration)
Closed-circuit Television Inspection – Crews will continue to
work throughout the Phase 2 area next week. Temporary lane closures will be implemented
as needed when crews are present.
Sequoyah Park – Morgan Construction and their subcontractors continue to
rehabilitate the existing wastewater main and manholes in Sequoyah Park. See
the attached map showing current work corridors within the park. The park, all
entrances and parking areas, and boat ramp remain open during this work. Morgan
Construction is also maintaining a fenced area in the middle parking lot for
equipment and materials storage. KUB has coordinated work in the park with City
of Knoxville Parks and Recreation and the Kingston Pike Sequoyah Hills
Association. Informational banners have been placed in the park
entrances/parking areas to provide park visitors with details about the
wastewater rehabilitation work. Updates on the progress of work in the park
will be posted weekly and as needed on this blog site.
Natural Gas System Work – Crews have resumed natural gas
inspection and maintenance work at various locations throughout Sequoyah Hills.
This work may require short term traffic impacts in the immediate area where
crews are working.
Concord/Painter Avenue Third Creek Greenway
July 19, 2019 Update – Third Creek Greenway Trail Diversion – Wastewater
rehabilitation work requiring trail diversions continues on the section of the
Third Creek Greenway just west of S. Concord Street through July 2019.
The Third Creek Greenway remains open. Trail users are reminded to be aware
of the presence of equipment, vehicles, and workers in the area while this work
is completed. See attached map.
Friday, July 12, 2019
Sequoyah Hills Wastewater Project Update
July 12, 2019 UPDATE
–
Sequoyah Hills Wastewater Rehabilitation – Construction crews will work in the following areas next week with intermittent daily road closures between 7 a.m. – 5 p.m.:
Sequoyah Hills Wastewater Rehabilitation – Construction crews will work in the following areas next week with intermittent daily road closures between 7 a.m. – 5 p.m.:
- Kenesaw
Avenue between Woodland Drive and Iskagna Drive (intermittent
road closures as needed for paving and restoration)
- Keowee Avenue between Kenesaw Avenue and Talahi Drive
Crews
will also work on the following roads with intermittent lane closures
between 7 a.m. – 5 p.m.:
- Cherokee
Boulevard between Southgate Road and Scenic Drive (westbound lane closed
during daytime work hours with traffic flow detoured via Southgate Road,
Taliluna Avenue, South Garden Road, Navaho Road, and Scenic Drive)
- Eastbound
traffic flow on this stretch of Cherokee Boulevard and Sequoyah Greenway
will remain open at all times
- Navaho
Road between South Garden Road and Scenic Drive
- South
Garden Road between Navaho Road and Cherokee Boulevard
Crews
will also work in the following off-road easements with no traffic impacts:
- Easement
between Scenic Drive and Holloway Drive (wastewater rehabilitation and
restoration)
- Easement
between Holloway Drive and Whitlow Avenue (Wastewater rehabilitation and
restoration)
- Easement between Southgate Drive and Bluff View Road (Restoration)
Closed-circuit
Television Inspection – Crews will continue to work throughout the Phase 2 area next
week. Temporary lane closures will be implemented as needed when crews are
present.
Sequoyah
Park –
Morgan Construction and their subcontractors continue to rehabilitate the
existing wastewater main and manholes in Sequoyah Park. See the attached map
showing current work corridors within the park. The park, all entrances and
parking areas, and boat ramp remain open during this work. Morgan Construction
is also maintaining a fenced area in the middle parking lot for equipment and
materials storage. KUB has coordinated work in the park with City of Knoxville
Parks and Recreation and the Kingston Pike Sequoyah Hills Association. Informational
banners have been placed in the park entrances/parking areas to provide park
visitors with details about the wastewater rehabilitation work. Updates on the
progress of work in the park will be posted weekly and as needed on this blog
site.
Natural
Gas System Work – Natural gas work has been temporarily suspended in Sequoyah Hills
as crews have been shifted to work on another area on the system.
Homberg Drive Water Main Replacement Project
July 12, 2019 -- Work started
Tuesday, July 9, on Homberg Drive as opposed to starting on Kingston Pike as
previously announced. Crews began construction activities near the Homberg
Drive and Whitaker Drive intersection and move west along Homberg Drive. There
will be temporary lane shifts of Homberg Drive in the immediate work zone
through September 2019. Access to businesses and driveways will be maintained
while crews perform work on Homberg Drive. There will also be work completed on
a short section of S. Mohican Street at Homberg Drive. Kingston Pike will not
be impacted during this timeframe.
Fountain City Natural Gas Project Update
July 12, 2019 – Contractor crews started potholing
work to locate existing underground utilities and boring in sections of new
natural gas mains between the 1900 and 2100 blocks on Martha Berry Drive this
week. Construction will continue on Martha Berry Drive next week while also
starting to pothole and bore in new main between the 6400-block of Grove Drive
to the Rifle Range Road intersection.
Holston Hills Natural Gas Project
July 12, 2019 Update
– Contractor East
Tennessee Pipeline crews completed boring in sections of natural gas pipeline
on East Sunset Drive this past week. Post construction work will continue on
East Sunset Drive next week. Crews will also start work on S. Chilhowee Drive
near the Holston Drive intersection next week.
Concord Street/Painter Avenue/Third Creek Greenway Wastewater Project
July
12, 2019 Update – Third Creek
Greenway Trail Diversion – Wastewater rehabilitation work requiring trail
diversions continues on the section of the Third Creek Greenway just west of S.
Concord Street through July 2019. The Third Creek Greenway remains open. Trail users are
reminded to be aware of the presence of equipment, vehicles, and workers in the
area while this work is completed. See
attached map.
Friday, July 5, 2019
Homberg Drive Water Main Project
News Release
For Immediate Release
July 5, 2019
For more information, contact:
KUB
Communications
Revised
Construction Schedule for KUB Water System Improvements
Homberg
Drive
KUB has revised the construction schedule for work to upgrade the
water distribution system in the Kingston Pike and Homberg Drive area of
Bearden.
Work will begin Tuesday, July 9, on Homberg Drive as opposed to
Kingston Pike as previously announced. Crews will begin construction activities
near the Homberg Drive and Whitaker Drive intersection and move west along
Homberg Drive. There will be temporary lane shifts of Homberg Drive in the
immediate work zone through September 2019. Access to businesses and driveways
will be maintained while crews perform work on Homberg Drive. There will also
be work completed on a short section of S. Mohican Street at Homberg Drive.
Kingston Pike will not be impacted during this timeframe.
This project will replace more than 2,700 feet of aging pipe to
improve reliability for customers and replace fire hydrants in the area.
Appropriate signs and devices will be in place to alert vehicle
traffic to upcoming traffic changes. KUB asks commuters to be mindful of the
presence of construction equipment, materials, vehicles, and workers when
travelling through this area.
See the Homberg Drive map for
more details.
###