Holston Hills Natural Gas Project
July 19, 2019 Update
– Contractor East
Tennessee Pipeline crews sleeved in a new 4-inch natural gas main into the
abandoned 6-inch cast iron pipeline along S. Chilhowee Drive, starting at the
Holston Drive intersection and working south. Crews will install remaining new
pipe on S. Chilhowee Drive, to the E. Sunset Road intersection, next week. Post
construction pipeline cleaning work will continue on East Sunset Drive next
week.