Fountain City Natural Gas Project

July 19, 2019 – Contractor crews are nearing completion of new natural gas main installation along Martha Berry Drive. Crews will move next to Grove Drive to install a new main from Martha Berry Drive to Grove Villas Way. Potholing work to locate existing underground utilities also started on Mynatt Road this week and will continue on the section of Grove Drive from Martha Berry Drive east to Colonial Circle. Main installation will continue on Grove Drive next week, starting at Grove Villas Way and progressing north across Rifle Range Road to 2372 Mynatt Road.