July 26, 2019
– Construction progress was temporarily slowed by heavy rains in the region
earlier in the week. Next week, crews will install natural gas main on the
section of Grove Drive between Martha Berry Drive and Mynatt Road. Potholing
work to locate existing underground utilities is scheduled for Mynatt Road and
Grove Drive between Martha Berry Drive east to Colonial Circle.