Friday, July 26, 2019

Holston Hills Natural Gas Project

July 26, 2019 Update – Post construction pipeline cleaning wrapped up on E. Sunset Road this week. Contractor East Tennessee Pipeline crews will continue installing natural gas main and making tie-in connections to existing mains on S. Chilhowee Drive next week. Pending completion of installation, crews will begin pipeline cleaning work on S. Chilhowee Drive.