Friday, January 4, 2019

Depot Avenue Area Water Main Project

January 4, 2018 UPDATE – A second round of pressuring testing was completed this week on the entire length of new 36-inch water transmission main installed over the past year between Blackstock Avenue and E. Summit Hill Drive. Remaining work includes a repair in the shoulder area on the south side of Willow Avenue (east of the Patton Street intersection with no impacts to traffic) and connecting the new water transmission line to the existing main at the intersection of Patton Street and E. Summit Hill Drive. As part of this work, Patton Street will remain closed between Drew Avenue and E. Summit Hill Drive, and closure of the westbound curbside lane on E. Summit Hill Drive near the Patton Street intersection. One westbound lane and both eastbound lanes will remain open. Access to local businesses will also be maintained.

(Downtown) E. Summit Hill Drive Lane, Patton Street Road Closure [January 7-9] – KUB contract crews will implement the below traffic control measures from 7 a.m., Monday, January 7, through 5 p.m., Wednesday, January 9, as work is performed on the water distribution system in the area:
  • Westbound, curbside lane of E. Summit Hill Drive at the Patton Street intersection closed. One westbound lane and both eastbound lanes will remain open, as will turn access to area businesses.
  • Patton Street between Willow Avenue and Campbell Avenue closed. N. Central Street is the alternate route.
Flaggers and signs will be on site to assist with traffic control, and follow-up advisories will be issued as necessary.

No comments:

Post a Comment