Friday, December 27, 2019
South Knox Water & Wastewater Project Update
December 20, 2019 – KUB
contract crews will close a section of Davenport Road between Boggs Avenue and
Sherrod Road to through traffic continuously from 9 a.m., Monday, December 30,
through 3 p.m., Friday, March 27, 2020, as work is performed on both the water
distribution and wastewater collection system in the area. The roadway will
reopen on weekends and holidays, and local traffic access will be maintained.
Alternate routes include Atchley Street, Mimosa Avenue, and Sherrod
Road.
Friday, December 20, 2019
Holston-Chilhowee Area Wastewater Project (Mini-Basin 20A3)
December 20, 2019 – As a follow-up to construction notices
that were mailed to area customers recently, the start for this project has
been shifted to early- to mid-January 2020. Continue to follow this blog for
weekly updates once construction begins.
Old Kingston Pike Water Main Project
December
20, 2019 – KUB
Underground Construction crews have completed the installation of all new water
mains and customer service line connections along Old Kingston Pike, Staub St
and S. Forest Park Blvd. No work will be performed in this area until
early January 2020. To minimize future disruptions in this area, KUB will
follow the water main project with wastewater collection system upgrades in
this same area starting in January 2020. Affected customers will be notified
prior to the start of wastewater construction. Final overall paving and
restoration will take place at the conclusion of the wastewater project.
Fountain City Natural Gas Project
December 20,
2019 – Contractor
Classic City Mechanical will work in the following areas next week:
- Connecting sections of natural
gas mains at:
- Grove Drive and Tansy Lane
- Grove Drive and Belcourt Drive
- Grove Drive and Edonia Drive
- Ridgewood Road and Poplar
Place
- Ridgewood Rod and N. Broadway
- Edonia Drive and Ridgewood
Road
Holiday
Schedule – Contractor crews will not work December 24-25. Due to holiday
schedules, the next blog update will be posted on January 3, 2020.
Holston Hills Natural Gas Project
December 20,
2019 Update –Contractor
East Tennessee Pipeline crews will work in the following areas next week:
- Potholing to located existing
buried utility lines and boring in new sections of natural gas main
between 1120 Montview Road and Shady Dell Trail
- Customer service line
connections to the new natural gas main in the following areas:
- 5212, 5213, 5300, 5308, 5312,
5313, 5317, 5400 Green Valley Drive
Holiday
Schedule – Contractor crews will not work December 23-25. Due to holiday
schedules, the next blog update will be posted on January 3, 2020.
Sequoyah Hills Wastewater Project
December 20, 2019 UPDATE - Construction crews will work in the following areas next week
with intermittent road closures between 7 a.m. – 5 p.m.:
- Taliluna
Avenue between South Garden Road and Lakeland Drive
- Whitlow Avenue between Bluff View Road and Cedarhill Road
Crews
will also work in the following off-road easements with minimal traffic
impacts:
- Easements between Lakeland Drive and Taliluna Avenue
Holiday
Schedule – Contractor crews will not work the week of December 23-27 in the
Phase 2 area. Limited work will take place in the work zones identified on the
attached map the week of December 30-January 3. Full construction activities
will resume the week of January 6. Due to holiday schedules, the next blog
update will be posted on January 3, 2020.
Closed-circuit
Television Inspection – Crews will continue to work throughout the Phase 2 area next
week. Temporary lane closures will be implemented as needed when crews are present.
Manhole
Rehabilitation – Crews will work throughout the Phase 2 area next week.
Temporary lane closures will be implemented as needed when crews are present.
Sequoyah
Park –
Morgan Construction and their subcontractors continue to break down the bypass
pumping equipment and piping in the park. Cleanup and restoration of excavated
areas also continues in the park. See the attached map showing current work
corridors within the park. The park, all entrances and parking areas, and boat
ramp remain open during this work. Morgan Construction is also maintaining a
fenced area in the middle parking lot for equipment and materials storage. KUB
has coordinated work in the park with City of Knoxville Parks and Recreation
and the Kingston Pike Sequoyah Hills Association.
Natural
Gas System Work – Crews have resumed natural gas inspection and maintenance
work at various locations throughout Sequoyah Hills. This work may require
short term traffic impacts in the immediate area where crews are working.
Friday, December 13, 2019
Old Kingston Pike Water Main Project
December
13, 2019 – KUB
Underground Construction crews have completed the installation of all new water
mains and customer service line connections along Old Kingston Pike, Staub St
and S. Forest Park Blvd. Asphalt patching and restoration crews will
continue to work in the area through next week. Road closures and lane
shifts will continue in this area as needed. To minimize future disruptions in
this area, KUB will follow the water main project with wastewater collection
system upgrades in this same area starting in January 2020. Affected customers
will be notified prior to the start of wastewater construction. Final overall
paving and restoration will take place at the conclusion of the wastewater
project.
Fountain City Natural Gas Project
December 13, 2019 – Contractor Classic City Mechanical
will work in the following areas next week:
- Potholing to located existing
buried utility lines and boring in new sections of natural gas main in the
following areas:
- Ridgewood Road from Oak Road
to N. Broadway
- 5501-5524 Peyton Place
- Connecting sections of natural
gas mains at:
- Grove Park and Brabson Drive
- Grove Park and Walkup Drive
- 2901 Brabson Drive
- Edonia Drive and Weems road
- Edonia Drive and Gresham Road
- Edonia Drive and Van Horn Road
- Edonia Drive and Ridgewood
Road
- Customer service line
connections to the new natural gas main in the following areas:
- 5760-5909 Grove Drive
- 2900-2905 Edonia Drive
- 1910 & 1911 Martha Berry
Drive
Holston Hills Natural Gas Project
December 13,
2019 Update –Contractor
East Tennessee Pipeline crews will work in the following areas next week:
- Potholing to located existing
buried utility lines and boring in new sections of natural gas main
between 4701 and 4905 Westover Terrace and on Shady Lane between Shady Dell
Trail and Westover Terrace
- Customer service line
connections to the new natural gas main in the following areas:
- 5612, 5615, 5616, 5617
Crestwood Drive
- 5317, 5320, 5321, 5325 Shady
Dell Trail
Friday, December 6, 2019
Sequoyah Hills Wastewater Project
December 6, 2019 UPDATE – Construction crews will work in the following areas next week
with intermittent road closures between 7 a.m. – 5 p.m.:
- Taliluna
Avenue between South Garden Road and Lakeland Drive
- Whitlow Avenue between Bluff View Road and Cedarhill Road
Crews
will also work in the following off-road easements with minimal traffic
impacts:
- Easements between Lakeland Drive and Taliluna Avenue
Closed-circuit
Television Inspection – Crews will continue to work throughout the Phase 2 area next
week. Temporary lane closures will be implemented as needed when crews are
present.
Manhole
Rehabilitation – Crews will work throughout the Phase 2 area next week.
Temporary lane closures will be implemented as needed when crews are present.
Sequoyah
Park – Morgan
Construction and their subcontractors will begin to break down the bypass
pumping equipment and piping in the park next week. Cleanup and restoration of
excavated areas will also begin next week. See the attached map showing current
work corridors within the park. The park, all entrances and parking areas, and
boat ramp remain open during this work. Morgan Construction is also maintaining
a fenced area in the middle parking lot for equipment and materials storage.
KUB has coordinated work in the park with City of Knoxville Parks and
Recreation and the Kingston Pike Sequoyah Hills Association. Informational
banners have been placed in the park entrances/parking areas to provide park
visitors with details about the wastewater rehabilitation work. Updates on the
progress of work in the park will be posted weekly and as needed on this blog
site.
Natural
Gas System Work – Crews have resumed natural gas inspection and maintenance
work at various locations throughout Sequoyah Hills. This work may require short
term traffic impacts in the immediate area where crews are working.
Holston Hills Natural Gas Project
December 6,
2019 Update –Contractor
East Tennessee Pipeline crews will work in the following areas next week:
- Potholing to located existing
buried utility lines and boring in new sections of natural gas main
between 4701 and 4905 Westover Terrace and on Shady Lane between Shady
Dell Trail and Westover Terrace
- Customer service line
connections to the new natural gas main in the following areas:
- 5612, 5615, 5616, 5617
Crestwood Drive
- 5317, 5320, 5321, 5325 Shady
Dell Trail
- 5610 Far Vista Lane
Fountain City Natural Gas Project
December 6,
2019 – Contractor
Classic City Mechanical will work in the following areas next week:
- Potholing to located existing
buried utility lines and boring in new sections of natural gas main in the
following areas:
- Ridgewood Road from Oak Road
to N. Broadway
- 5501-5524 Peyton Place
- Connecting sections of natural
gas mains at:
- Brabson Drive and Walkup Drive
- Brabson Drive and Grove Park
Drive
- Edonia Drive and Grove Park
Drive
- Edonia Drive and Weems Road
- Edonia Drive and Gresham Road
- Edonia Drive and Van Horn
Drive
- Customer service line
connections to the new natural gas main in the following areas:
- 5760-5936 Grove Drive
- 2813 & 2822 Pruden Drive
- 1910 & 1911 Martha Berry
Drive
Old Kingston Pike Water Main Project
December
6, 2019 – KUB
Underground Construction crews have completed the installation of all new water
mains along Old Kingston Pike, Staub St and S. Forest Park Blvd. Crews
completed service connections along S. Forest Park Boulevard this past week,
and work will continue on customer service lines and fire hydrant connections
along Old Kingston Pike in the coming days. Road closures and lane shifts
will continue in this area as crews dig to connect customer service lines to
the new main and roadway asphalt patching follows. All construction associated
with the water lines is scheduled for completion prior to the upcoming holidays. To
minimize future disruptions in this area, KUB will follow the water main
project with wastewater collection system upgrades in this same area starting
in early January. Affected customers will be notified prior to the start of
wastewater construction. Final paving and restoration will take place at the
conclusion of the wastewater project.