Friday, December 6, 2019

Holston Hills Natural Gas Project


December 6, 2019 Update –Contractor East Tennessee Pipeline crews will work in the following areas next week:
  • Potholing to located existing buried utility lines and boring in new sections of natural gas main between 4701 and 4905 Westover Terrace and on Shady Lane between Shady Dell Trail and Westover Terrace
  • Customer service line connections to the new natural gas main in the following areas:
    • 5612, 5615, 5616, 5617 Crestwood Drive
    • 5317, 5320, 5321, 5325 Shady Dell Trail
    • 5610 Far Vista Lane