December 6,
2019 Update –Contractor
East Tennessee Pipeline crews will work in the following areas next week:
- Potholing to located existing
buried utility lines and boring in new sections of natural gas main
between 4701 and 4905 Westover Terrace and on Shady Lane between Shady
Dell Trail and Westover Terrace
- Customer service line
connections to the new natural gas main in the following areas:
- 5612, 5615, 5616, 5617
Crestwood Drive
- 5317, 5320, 5321, 5325 Shady
Dell Trail
- 5610 Far Vista Lane