Holston Hills Natural Gas Project

December 20, 2019 Update –Contractor East Tennessee Pipeline crews will work in the following areas next week:
  • Potholing to located existing buried utility lines and boring in new sections of natural gas main between 1120 Montview Road and Shady Dell Trail
  • Customer service line connections to the new natural gas main in the following areas:
    • 5212, 5213, 5300, 5308, 5312, 5313, 5317, 5400 Green Valley Drive
Holiday Schedule – Contractor crews will not work December 23-25. Due to holiday schedules, the next blog update will be posted on January 3, 2020.