- Taliluna
Avenue between South Garden Road and Lakeland Drive
- Whitlow Avenue between Bluff View Road and Cedarhill Road
Crews
will also work in the following off-road easements with minimal traffic
impacts:
- Easements between Lakeland Drive and Taliluna Avenue
Holiday
Schedule – Contractor crews will not work the week of December 23-27 in the
Phase 2 area. Limited work will take place in the work zones identified on the
attached map the week of December 30-January 3. Full construction activities
will resume the week of January 6. Due to holiday schedules, the next blog
update will be posted on January 3, 2020.
Closed-circuit
Television Inspection – Crews will continue to work throughout the Phase 2 area next
week. Temporary lane closures will be implemented as needed when crews are present.
Manhole
Rehabilitation – Crews will work throughout the Phase 2 area next week.
Temporary lane closures will be implemented as needed when crews are present.
Sequoyah
Park –
Morgan Construction and their subcontractors continue to break down the bypass
pumping equipment and piping in the park. Cleanup and restoration of excavated
areas also continues in the park. See the attached map showing current work
corridors within the park. The park, all entrances and parking areas, and boat
ramp remain open during this work. Morgan Construction is also maintaining a
fenced area in the middle parking lot for equipment and materials storage. KUB
has coordinated work in the park with City of Knoxville Parks and Recreation
and the Kingston Pike Sequoyah Hills Association.
Natural
Gas System Work – Crews have resumed natural gas inspection and maintenance
work at various locations throughout Sequoyah Hills. This work may require
short term traffic impacts in the immediate area where crews are working.