Friday, December 20, 2019

Fountain City Natural Gas Project

December 20, 2019 – Contractor Classic City Mechanical will work in the following areas next week:
  • Connecting sections of natural gas mains at:
    • Grove Drive and Tansy Lane
    • Grove Drive and Belcourt Drive
    • Grove Drive and Edonia Drive
    • Ridgewood Road and Poplar Place
    • Ridgewood Rod and N. Broadway
    • Edonia Drive and Ridgewood Road
Holiday Schedule – Contractor crews will not work December 24-25. Due to holiday schedules, the next blog update will be posted on January 3, 2020.