Friday, December 6, 2019

Fountain City Natural Gas Project


December 6, 2019 – Contractor Classic City Mechanical will work in the following areas next week:
  • Potholing to located existing buried utility lines and boring in new sections of natural gas main in the following areas:
    • Ridgewood Road from Oak Road to N. Broadway
    • 5501-5524 Peyton Place
  • Connecting sections of natural gas mains at:
    • Brabson Drive and Walkup Drive
    • Brabson Drive and Grove Park Drive
    • Edonia Drive and Grove Park Drive
    • Edonia Drive and Weems Road
    • Edonia Drive and Gresham Road
    • Edonia Drive and Van Horn Drive
  • Customer service line connections to the new natural gas main in the following areas:
    • 5760-5936 Grove Drive
    • 2813 & 2822 Pruden Drive
    • 1910 & 1911 Martha Berry Drive