Holston-Chilhowee Area (Mini-basin 20A3) Wastewater Project

February 14, 2020 – KUB’s contractor for this project, Morgan Construction, worked on Grata Road and Comanche Drive this past week. Due to time lost to weather this past week, the contractor will work on these same streets this Saturday, February 15. The crew is scheduled to move to Silva Drive next week. As a reminder, due to the location of some wastewater pipes and manholes under area roadways, temporary lane and/or road closures may be needed in the immediate area where crews are working for the duration of this project. This project is scheduled for completion by December 2020.