Friday, February 14, 2020
Holston-Chilhowee Area (Mini-basin 20A3) Wastewater Project
February
14, 2020 – KUB’s
contractor for this project, Morgan Construction, worked on Grata Road and
Comanche Drive this past week. Due to time lost to weather this past week, the
contractor will work on these same streets this Saturday, February 15. The crew
is scheduled to move to Silva Drive next week. As a reminder, due to the
location of some wastewater pipes and manholes under area roadways, temporary
lane and/or road closures may be needed in the immediate area where crews are
working for the duration of this project. This project is scheduled for
completion by December 2020.