S. Knoxville Water & Wastewater Project (Mini-basic 40C1)

February 14, 2020 – KUB’s contractor, Portland Utilities, continued installing sections of new water main on Davenport Road, between Sherrod Road and Boggs Avenue, this past week. Crews will continue installation and begin testing this section of water main next week before beginning saw-cutting/construction prep on Davenport Road between Boggs Avenue and progressing north toward Sevier Avenue. Road closures will continue in the immediate work zone daily from 7:30 a.m. – 6 p.m. next week. Water main installation has been completed on Boggs Avenue; however, testing, connecting customer service lines, and tying in to the existing main at the Jones Street intersection remains in this area over the next several weeks.