Taliluna Avenue between
South Garden Road and Lakeland Drive
·
Whitlow Avenue between
Bluff View Road and Cedarhill Road
Closed-circuit
Television Inspection – Crews will continue to work throughout the Phase 2 area next
week. Temporary lane closures will be implemented as needed when crews are
present.
Manhole
Rehabilitation – Crews will work throughout the Phase 2 area next week.
Temporary lane closures will be implemented as needed when crews are present.
Sequoyah
Park –
Break-down of bypass pumping equipment and piping is complete. Cleanup and
restoration of disturbed areas will continue as weather allows over the next
several weeks. See the attached map showing current work corridors within the
park. The park, all entrances and parking areas, and boat ramp remain open
during this work. Morgan Construction continues to maintain a fenced area in
the middle parking lot for equipment and materials storage. KUB has coordinated
work in the park with City of Knoxville Parks and Recreation and the Kingston Pike
Sequoyah Hills Association. Informational banners have been placed in the park
entrances/parking areas to provide park visitors with details about the
wastewater rehabilitation work. Updates on the progress of work in the park
will be posted weekly and as needed on this blog site.
Natural
Gas System Work – Crews are scheduled to resume natural gas inspection and maintenance
work at various locations throughout Sequoyah Hills in February. This work may
require short term traffic impacts in the immediate area where crews are
working.