February
7, 2020 – KUB’s
contractor, Portland Utilities, continued installing sections of new water main
on Davenport Road, between Sherrod Road and Boggs Avenue, this past week. Crews
will look to finish installation and begin testing this section of water main
next week before beginning saw-cutting/construction prep on Davenport Road
between Boggs Avenue and progressing north toward Sevier Avenue. Road closures
will continue in the immediate work zone daily from 7:30 a.m. – 6 p.m. next
week. Water main installation has been completed on Boggs Avenue; however,
testing, connecting customer service lines, and tying in to the existing main
at the Jones Street intersection remains in this area over the next several
weeks.