Friday, January 10, 2020

South Knoxville Water Main Replacement & Wastewater Rehabilitation (Mini-Basin 40C1) Update


January 10, 2020 – 

KUB’s contractor, Portland Utilities, has been performing pre-construction prep work, including saw-cutting of asphalt, this past week. Construction prep work will continue next week. Water installation is scheduled to begin on Boggs Avenue (at the Davenport Road intersection and progressing west) next week. Continue to follow this blog for weekly updates once construction begins.

Holston-Chilhowee Area Wastewater Rehabilitation (Mini-Basin 20A3) Update


January 10, 2020 – 

As a follow-up to construction notices that were mailed to area customers recently, the start for this project has been shifted to late January 2020. Continue to follow this blog for weekly updates once construction begins.

Old Kingston Pike Water Main Replacement Update


January 10, 2020 – 

KUB Underground Construction crews have completed the installation of all new water mains and customer service line connections along Old Kingston Pike, Staub St and S. Forest Park Blvd. To minimize future disruptions in this area, KUB will follow the water main project with wastewater collection system upgrades in this same area starting in late January 2020. Affected customers will be notified prior to the start of wastewater construction. Final overall paving and restoration will take place at the conclusion of the wastewater project.