March 8, 2019 Update – Contractor Mobilizes Onsite
– KUB contractor crews finished
closed-circuit TV inspections of gravity wastewater pipes in the area this past
week. Excavation work continues at the intersection of Painter Avenue and
Concord Street. Intermittent lane shifts will be implemented on Concord Street
as needed next week in association with manhole replacement work. Two-way
traffic will be maintained at all times on Concord Street. Painter Avenue will
remain closed to vehicle through traffic for approximately two more weeks.
Alternate routes around the closure zone will include Jersey Avenue, Lindsay
Place, and Sullins Street.
Following
completion of work on Painter Avenue, a closure of the Third Creek Greenway
lasting approximately one week will be required between the west entrance/exit
to Tyson Park and the trail split near Safety City. A detour will be set up via
Painter Avenue while this section of greenway is closed. All traffic and
greenway impacts will be communicated by KUB and the contractor via onsite
signage, media advisories, and on social media platforms. Construction
affecting Painter Avenue and the Third Creek Greenway will not be performed at
the same time, and related closures will not occur during the same period.
See map on right hand side of this blog.