Noelton Drive Water Main
Replacement Project – KUB Underground Construction crews have
completed all water main installation, testing, and customer service line
connections on Noelton Drive, Chippewa Circle, and Dogwood Lane. Paving and
restoration will continue on these streets over the next several weeks as
weather conditions allow.
Sequoyah Hills
Wastewater Rehabilitation Phase 1 – Manhole rehabilitation
crews will continue to work at various locations throughout the Phase 1 area.
Temporary lane closures may be needed in the immediate area where crews are
working.
Sequoyah
Hills Wastewater Rehabilitation Phase 2 – KUB Phase 2 contractor, Morgan
Construction, completed wastewater system rehabilitation work on Kenesaw
Avenue, Keowee Avenue, and Taliluna Avenue this past week. Paving and
restoration work requiring intermittent lane closures between 7 a.m. – 5 p.m.
will continue on these streets next week. The contractor will begin
rehabilitation work on the section of Sequoyah Avenue between Agawela Avenue
and Southgate Road next week. This section of Sequoyah Avenue will be closed to
through traffic between 7 a.m. – 5 p.m.
Sequoyah
Park –
Morgan Construction is scheduled to begin work to rehabilitate the existing
wastewater main and manholes in Sequoyah Park in late March. The park and
parking areas will remain open during this work. More information will be
communicated as details are finalized in the coming days. Appropriate
traffic control measures, including signs and barriers, will be in place to
assist with traffic flow. Access to driveways will be maintained. All lanes
will reopen to normal traffic flow outside of listed work hours and on
weekends. The Sequoyah Greenway will not be affected by this work.
(Sequoyah Hills) Sequoyah
Hills Area Road Closures [February 18-22] – KUB contract crews will implement the below
indicated road closures,
from 7 a.m. – 5 p.m., starting Monday, March 18, through Friday, March 22, as work continues on the wastewater collection system in
the area:
- Sequoyah Avenue between Southgate Road and Agawela
Avenue – closed daily during work hours.
- Taliluna Avenue between Kenesaw Avenue and Tugaloo
Drive – closed intermittently as needed.
- Kenesaw Avenue between Woodland Drive and Iskagna Drive
– closed intermittently as needed.
- Keowee Avenue between Southgate Road and Agawela Avenue
– closed intermittently as needed.
Access to area homes will be maintained, and barricades and signs
will be on site to assist with traffic control. Follow-up advisories will be
issued as necessary.
No comments:
Post a Comment